While portions of the construction industry are starting to see some relief due to the end to pandemic-related restrictions and immediate solutions to port delays and trucker shortages; protracted supply chain issues, skyrocketing inflation, and geopolitical tensions globally indicate another challenging year in 2022. In this issue, we explore the current issues facing our National Healthcare Team, transportation, economics, and the geopolitical forefront and offer solutions to mitigating these impacts on construction.
AT THE PROJECT LEVEL
How much today? – Month-to-month pricing is changing dramatically. A project that was procured even six months ago is considerably different than a new project today. For this reason, Sam has created a national healthcare dashboard for our preconstruction teams, design partners, and clients which includes every project across the country we price in today’s market – regardless of their level of design – to ensure our data is always live with today’s costs. Waiting for formal GMP or finished cost data is
too late with the volatility we are
facing today.
How much tomorrow?
The truth is no one has a crystal ball to foresee the future. Current trends have increased construction costs at a scale of 1%+ per month, which is the rate we have been advising our clients to expect for additional funding as we chart construction costs over the project’s life cycle. This rate is historically high as ANNUAL escalation over the previous
10 years was a steady 2-3% per YEAR. We have seen time after time that “hoping” for better pricing is simply not happening, so formally reconciling funding with the current economic environment is the reality and should be supported with an appropriate contingency strategy upfront.
So what do we need to do?
The short answer—time to redesign is too expensive. Waiting for an economic pause or redesigning an over-budget project to reduce costs is not realistic right now. The cost of time and the escalation exposure routinely outweighs the benefits of any potential incremental savings. For example, a three month pause that reduced cost by 3% will be wiped out by the 1% per month escalation impact to the project over the same span.
We advise clients to scale back original programmatic baseline requirements to the bare bones of the project’s initial business case at the start. We need to know the acceptable minimum scope and eliminate the “would-be-nice-to-have” items. Misalignment of old funding requests with current market conditions in the norm and we need to know how “small” we can get at programmatic level for the client to see what escalation to date can be countered by reduction of space. As stated before, the escalation impact does not grant us the flexibility to
pause and reign in programmatic
creep once in design – this must be done at concept.
“How much tomorrow” is a team decision on risk tolerance on how to handle future escalation. Some projects have a single board ask, whereas some projects inform the board of the outstanding risk and choose to fund the future escalation as a separate financial source. The project specific funding expectation will be the backbone of where and how escalation risk and its associated contingency value will be established and housed.
After baseline programmatic requirements and future escalation risk are financially addressed at project formation, projects can now delineate scope development versus escalation impact in the design phase. Clear delineation of adding client requested “nice to have” items are tracked
against a dedicated funding source, whereas evolving market conditions are tracked against a separate escalation contingency. This organizes the
project financials for “controllable” scope management versus an “uncontrollable” market risk mitigation in the form of escalation contingency health assessments balanced with market conditions as they become known in design.
AT THE REGIONAL LEVEL
These project-level determinations are impacted by what else is going on in your region. We are seeing megaprojects in towns such as Austin or Phoenix with 1M+ sf projects creating trade-specific strains in the build community. This can have a direct effect on your project cost. We maintain schedules of all large projects – not just ours – going on in each of our markets to proactively mitigate impacts of labor shortages and concentrated escalation. We advise to secure trade partners with early procurement strategies, partner with vendors for bulk material purchasing, and implement innovative prefabrication strategies to alleviate supply chain bottle necks.
Market Overview
Architectural billings grew month-over-month for all three months of the first quarter, however, construction spending and project starts both declined as material costs reached their highest level on record.
“Current trends have increased construction costs at a scale of 1+% per month, which is the rate we have been advising our clients to expect for additional funding as we chart construction costs over the project’s life. This rate is historically high as ANNUAL escalation over the previous 10 years was a steady 2-3% per YEAR. ”
- Sam O’Connor, Preconstruction Director – National Healthcare
Bottom Line for Our Clients and Partners
With price escalations even higher than those following the great financial crisis over a decade ago, now more than ever, we are navigating uncharted waters. While hopeful that prices will soon reach an inflection point and will retreat as more production comes online, supply chains are reconnected, and inventory levels are replenished, the timing of such downward pressure remains contingent on the end of the public health crisis along with a normalization of supply and demand.
TRANSPORTATION
Driver shortages, delays at the port and rising gas prices headlined transportation in 2022’s first quarter. These disruptions to the supply chain have left the construction industry scrambling to secure materials, and in some cases, change design and material selections at the last minute so as not to cause unnecessary project schedule delays. For the latest on how the strains at the port and domestic shipping are being addressed, click LEARN MORE.
Learn more
1575
1475
1375
1275
1175
1075
975
National Construction Indicators
ACTIVITY & PRICING METRICS
hover to explore more
Q4 2011
0.50%
Q1 2012
0.58%
Q2 2012
-0.06%
Q3 2012
0.99%
Q4 2012
0.70%
Q1 2013
1.33%
Q2 2013
0.85%
Q3 2013
0.68%
Q4 2013
0.94%
Q1 2014
1.04%
Q2 2014
0.61%
Q3 2014
1.13%
Q4 2014
-0.33%
Q1 2015
0.52%
Q2 2015
0.55%
Q3 2015
1.52%
Q4 2015
0.05%
Q1 2016
0.25%
Q2 2016
3.03%
Q3 2016
0.74%
Q4 2016
0.54%
Q1 2017
1.06%
Q2 2017
0.72%
Q3 2017
1.21%
Q4 2017
0.65%
Q1 2018
1.35%
Q2 2018
2.11%
Q3 2018
0.70%
Q4 2018
0.90%
Q1 2019
0.72%
Q2 2019
0.82%
Q3 2019
0.69%
Q4 2019
0.45%
Q1 2020
0.02%
Q2 2020
0.01%
Q3 2020
0.04%
Q4 2020
1.11%
Q1 2021
4.03%
Q2 2021
5.38%
Q3 2021
0.18%
Q4 2021
2.93%
Index #
2011
2013
2014
2015
2016
2017
2018
2019
2020
2021
2012
Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris. Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua.
Current Events
Learn more
Learn more
ECONOMICS
We’re all feeling escalation at the project level, but what is causing it at the macroeconomic level? The national health crisis created by COVID-19 caused the federal government to use their known mechanisms to stimulate the economy, which ultimately resulted in record-breaking inflation. To read about the government’s plan to make economic corrections and how our experts think these will impact construction, click LEARN MORE.
GEOPOLITICAL
Numerous global factors play into the prices of construction materials. As pandemic-related restrictions were eased in late 2021 and early 2022 saw some relief in shipping gridlock, hopes were high that the global supply chain would see delay and price corrections. Instead, the war in Ukraine and new COVID-related lockdowns in China both caused havoc late in the quarter. To read more about the strains and how we’re mitigating the impact to construction, click LEARN MORE.
Lorem Ipsum Dolor
Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. Lorem ipsum dolor sit amet, consectetur adipiscing elit.
Learn more
Lorem Ipsum Dolor
Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. Lorem ipsum dolor sit amet, consectetur adipiscing elit.
Learn more
Lorem Ipsum Dolor
Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. Lorem ipsum dolor sit amet, consectetur adipiscing elit.
Learn more
Lorem Ipsum Dolor
Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. Lorem ipsum dolor sit amet, consectetur adipiscing elit.
Learn more
Lorem Ipsum Dolor
Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. Lorem ipsum dolor sit amet, consectetur adipiscing elit.
Learn more
Lorem Ipsum Dolor
Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum. Lorem ipsum dolor sit amet, consectetur adipiscing elit.
Learn more
CLICK HERE TO DOWNLOAD MARKET-SPECIFIC DATA
Santa Clara
Williston
Minneapolis
Omaha
Kansas City
Denver
Oklahoma
Dallas
Austin
Houston
Nashville
Atlanta
Charlotte
Tampa
Savannah
Click on an office below to download their in-depth market report.
PORTLAND
Phoenix
To subscribe to future
issues of The Look Ahead,
please fill out this form.
Sam O’Connor, Preconstruction Director – National Healthcare, describes what his team is doing to guide clients through the current staggering escalation. His clients are asking the same three questions consistently: How much does this project cost today; How much is it tomorrow; What can we do to keep moving forward?
CLICK HERE to learn more.
2022Q1 THE LOOK AHEAD
Healthcare Spotlight
PORT DELAYS
According to Port of Los Angeles Executive Director Gene Seraka, unloading ships at ports on the West Coast has become more efficient and fewer workers are missing shifts due to COVID-19 infections.¹ In addition, smaller ports around the country such as Cleveland (+ 69%), Galveston (+ 13%) and Jacksonville (+ 10%) have seen huge increases in their traffic helping alleviate some backlog at larger ports. ²
TRUCKER SHORTAGES
The Trucking Action Plan rolled out in December of 2021 made necessary and quick corrections to some of the challenges facing the trucking industry. Those issues include high turnover rates, an aging workforce, and long hours. With 72% of our goods shipped via truck, the need for good, safe, and stable trucking jobs is critical. The Transportation Action Plan offers accelerated programs for truckers to receive training and their CDLs, career initiatives, and veteran-focused recruitment.³ The result has been pay increases between 7-12% in the past year. The Department of Transportation provided $57 million to help states expedite commercial driver’s license issuances, resulting in a 112% increase in CDL processing in the first two months of 2022 as compared to the same time period the prior year.
Sources:
1) Supplychaindrive.com
2) Fox Business
3) Whitehouse.gov
4) TransportationDrive.com
The Federal Reserve is responsible for maintaining financial stability in the US. They grew their balance sheet and lowered interest rates, which provided a quick stimulus to our economy and created short-term demand to combat the pandemic’s economic effects. However, historically high inflation has been the long-term consequence.
One way the Fed combats inflation is to raise the Federal Funds Target Range, which in turn raises short-term interest rates. Another way they reduce inflation is to reduce the size of their balance sheet. The Fed is currently doing both.
INTEREST RATES
On March 15, 2022, the Fed raised the overnight lending rate 0.25 points and outlined the potential for seven more rate hikes before the end of the year. Interest rates act as a governor on the economy. When the Fed raises the interest rate, the goal is to slow down spending, which lowers demand –in turn eventually lowering prices as well.
BALANCE SHEET
In March of 2020, the US balance sheet totaled $4.7 trillion, and today (March 2022) it sits at $8.9 trillion. They plan to deploy “rapid reduction” strategies, which typically include selling securities and then not reinvesting in mature securities. This puts upward pressure on long-term rates as demand decreases, also causing prices to decrease.
The escalation we are seeing in construction is not driven by just inflation. Supply chain issues, politics, natural disasters, and technology also impact escalation. For construction projects in their infancy, we are consistently asked if and when we will see inflation and escalation corrections in the economy, and if it would be worthwhile to delay a project start in hopes of lower material prices. Truthfully, even the most influential experts are not comfortable making those predictions at this time. Each project team, including the design team and owner, will need to put together a market-specific strategy weighing a delayed project start against other project priorities such as construction timing requirements, speed-to-market options, and replacing old assets.
The type of facility proposed is also important. As we outlined in our healthcare market focus above, waiting is not worth the potential impacts, as healthcare typically stays steady through booming times and economic dips. The overall volume warrants moving ahead with an escalation strategy rather than delaying starts.
Russia’s invasion of Ukraine has served the global supply chain a double punch of raw material shortages and cargo disruption. For example, the two countries account for 60% of the world’s pig iron (a core component in 70% of the world’s steel) supply, collectively. Steel prices were already up 89% between December 2020 and December 2021 and the shortage of this raw material is driving them even higher. In addition, the sanctions imposed on Russia and their warfare tactics have closed shipping ports, air cargo routes, and destroyed railroads, further complicating an already fragile supply chain and global distribution climate.
In March, the Chinese city of Shenzhen was placed on total lockdown to control another outbreak of COVID causing the Shenzhan port of Yantian to face another shut down. Yantian is the fourth largest port in the world and another shut down will inevitably cause further ripples throughout global shipping.¹ To offer some context to the actual costs the pandemic has doled out to shipping, according to the Freightos index, the cost of sending a standard shipping container from China to Los Angeles rose by 20 percent in January and February to $16,353. This is an increase of 12 times the cost in the months before the pandemic. ²
We’re having conversations early and often with our clients and design partners to handle these global issues at a local level. By keeping tabs on what materials are most impacted, we can put a lead-time plan in place or suggest alternative materials that may not be facing these same challenges.
1) Fortune.com
2) Washingtonpost.com
4
For the full experience or to download the report access this experience on a computer or on a tablet.
Atlanta
Numerous global factors play into the prices of construction materials. As pandemic-related restrictions were eased in late 2021 and early 2022 saw some relief in shipping gridlock, hopes were high that the global supply chain would see delay and price corrections. Instead, the war in Ukraine and new COVID-related lockdowns in China both caused havoc late in the quarter. To read more about the strains and how we’re mitigating the impact to construction, click LEARN MORE.
Numerous global factors play into the prices of construction materials. As pandemic-related restrictions were eased in late 2021 and early 2022 saw some relief in shipping gridlock, hopes were high that the global supply chain would see delay and price corrections. Instead, the war in Ukraine and new COVID-related lockdowns in China both caused havoc late in the quarter. To read more about the strains and how we’re mitigating the impact to construction, view this experience on a computer or tablet.
We’re all feeling escalation at the project level, but what is causing it at the macroeconomic level? The national health crisis created by COVID-19 caused the federal government to use their known mechanisms to stimulate the economy, which ultimately resulted in record-breaking inflation. To read about the government’s plan to make economic corrections and how our experts think these will impact construction, view this experience on a computer or tablet.
Driver shortages, delays at the port and rising gas prices headlined transportation in 2022’s first quarter. These disruptions to the supply chain have left the construction industry scrambling to secure materials, and in some cases, change design and material selections at the last minute so as not to cause unnecessary project schedule delays. For the latest on how the strains at the port and domestic shipping are being addressed, view this experience on a computer or tablet.
Austin
Williston
Tampa
Santa Clara
Portland
Phoenix
Omaha
Oklahome City
Nashville
Minneapolis
Kansas City
Houston
Denver
Dallas
Charlotte
Savannah